dbeard@dominionpost.com MORGANTOWN – The Public Service Commission Consumer Advocate Division on Feb. 20 found some shortcomings in NextEra Energy Transmission MidAtlantic’s revised proposed public notice regarding its MidAtlantic Resiliency Link […]
Tag: WV PSC
MARL line receives 12 letters of support
dbeard@dominionpost.com MORGANTOWN – In an unusual turn of events, 12 people have filed letters of support for the MARL transmission line with the Public Service Commission. However, only one letter […]
PSC Consumer Advocate Division finds problems in NextEra’s proposed public notice filing for MARL
dbeard@dominionpost.com MORGANTOWN – The Public Service Commission’s Consumer Advocate Division found additional flaws in NextEra Energy Transmission MidAtlantic’s revised proposed public notice regarding its MidAtlantic Resiliency Link Project (MARL). Some, […]
PSC grants siting certificate for Brandonville Solar project
dbeard@dominionpost.com MORGANTOWN – The 1,154-acre Brandonville Solar project has received the green light from the Public Service Commission. “The commission has thoroughly reviewed all filings in this matter, including the […]
PSC orders hearing in PSD1 rate-hike case
dbeard@dominionpost.com MORGANTOWN – The Public Service Commission has ordered a public hearing on the rate-increase request filed by Preston County Public Service District No. 1. “Given the level of protests, […]
NextEra submits amended proposed public notice to PSC: Addresses concerns raised by PSC staff
dbeard@dominionpost.com In response to objections filed by Public Service Commission staff, NextEra Energy Transmission MidAtlantic has submitted a revised proposed public notice regarding its MidAtlantic Resiliency Link Project (MARL) to […]
Mon Power, Potomac Edison seek PSC OK for gas-fired plant at Fort Martin
dbeard@dominionpost.com MORGANTOWN – FirstEnergy sisters Mon Power and Potomac Edison want to build a new gas-fired power plant at their Fort Martin site outside Morgantown. The companies have filed with […]
PSC staff objects to NextEra’s MARL application proposed public notice: Seeks more details
dbeard@domininopost.com MORGANTOWN – Public Service Commission staff on Friday filed an objection to NextEra Energy Transmission MidAtlantic’s application for a PSC permit for its MidAtlantic Resiliency Link Project (MARL). The […]
A look at some MARL details, and some opposition
dbeard@dominionpost.com MORGANTOWN – NextEra Energy Transmission MidAtlantic’s application for a Public Service Commission permit for its MidAtlantic Resiliency Link Project (MARL) transmission line spans more than 3,000 pages. We are […]
NextEra files for PSC permit for MARL project
dbeard@dominionpost.com MORGANTOWN – NextEra Energy Transmission MidAtlantic has applied with the state Public Service Commission for a certificate of public convenience and necessity for its MidAtlantic Resiliency Link Project (MARL). […]