MUB's Cheat Lake treatment plant project nearing midway point

MORGANTOWN – The Morgantown Utility Board expansion of its Cheat Lake Wastewater Treatment Plant is about halfway done. “The project is 48% complete. The project is on schedule for its final completion date of Aug. 31, 2027,” MUB Construction Manager Jeremiah Johnson explained. ...