MORGANTOWN – Six binders totaling more than 3,000 pages. That, in physical form, is the NextEra Energy Transmission MidAtlantic application for a certificate of public convenience and necessity currently before the […]
Tag: MARL
PSC staff objects to NextEra’s MARL application proposed public notice: Seeks more details
dbeard@domininopost.com MORGANTOWN – Public Service Commission staff on Friday filed an objection to NextEra Energy Transmission MidAtlantic’s application for a PSC permit for its MidAtlantic Resiliency Link Project (MARL). The […]
A look at some MARL details, and some opposition
dbeard@dominionpost.com MORGANTOWN – NextEra Energy Transmission MidAtlantic’s application for a Public Service Commission permit for its MidAtlantic Resiliency Link Project (MARL) transmission line spans more than 3,000 pages. We are […]
NextEra files for PSC permit for MARL project
dbeard@dominionpost.com MORGANTOWN – NextEra Energy Transmission MidAtlantic has applied with the state Public Service Commission for a certificate of public convenience and necessity for its MidAtlantic Resiliency Link Project (MARL). […]
NextEra files renewed notice of intent to apply for PSC permit for MARL project
dbeard@dominionpost.com MORGANTOWN – NextEra Energy Transmission MidAtlantic told the state Public Service Commission on Monday that it once again intends to apply for a certificate of public convenience and necessity […]
Officials disappointed, not surprised by proposed MARL route
MORGANTOWN — County commissioners in Preston and Hampshire counties said they were disappointed to see the route proposed for NextEra Energy Transmission’s MidAtlantic Resiliency Link transmission project run across their […]
NextEra picks MARL path through Mon, Preston counties
MORGANTOWN — Two segments in Monongalia County and the entire width of northern Preston County are included in NextEra Energy Transmission’s preferred route for its MidAtlantic Resiliency Link transmission project. […]
A look at MARL and PJM’s B3800 project series
dbeard@dominionpost.com MORGANTOWN – An error in a Potomac Edison filing with the state Public Service Commission briefly led to public belief that two separate transmission line projects– Potomac Edison’s and […]
PSC answers Preston County Commission objections to MARL project
dbeard@dominionpost.com MORGANTOWN – Last week, the Preston County Commission sent a letter – just over two pages – to the state Public Service Commission listing its objects to the proposed […]
Public files protests against MARL line with WV PSC
dbeard@dominionpost.com MORGANTOWN – Public protests against the proposed MARL transmission line have begun pouring in to the state Public Service Commission – 158 so far. NextEra Energy Transmission MidAtlantic told […]