MUB expects to begin Cheat Lake plant startup in 2026
Trending
MORGANTOWN - According to Morgantown Utility Board General Manager Mike McNulty, the newly expanded portion of the Cheat Lake Wastewater Treatment Plant will start coming online by the end of the year.
In a Nov. 17 update to the utility board, McNulty said MUB leadership recently toured the project site, and noted training and commissioning of the new equipment is underway.
"Site retaining walls have been completed and grading topsoil placement is underway on the west side of the new plant. Site electric is completed. The generator has been installed. The UV structure is completed. Phase one of the control building is complete, and the admin building is near completion," he said. "The thought was that the new plant would begin treating flows in November, but I think that's going to be pushed off until December. Everything is moving forward."
The handoff of flows from the existing plant to the expansion marks a significant step as improvements to the old plant cannot begin until it's taken offline.
As you might expect, that transition is far more complicated than simply throwing a switch.
"That is definitely not an easy process," a MUB spokesperson told The Dominion Post, explaining representatives from contractor Mele & Mele & Sins, project engineering firm Strand Associates, MUB, and the various equipment manufacturers will likely be on site to assist with the start-up process.
"It is expected that this process will take approximately 30 days to complete if everything goes smoothly."
MUB awarded the construction project to Braddock, Pennsylvania-based Mele & Mele & Sons for just over $36 million in late 2024. The total cost estimate for the project is approximately $46 million.
The project is both growing the plant's capacity from 750,000 gallons per day to 1.75 million gallons per day and expanding its physical footprint onto a 12.7-acre property located behind the existing plant and between Sunset Beach Road and the Chestnut Ridge Church parking lot.
MUB purchased that land for $1.8 million in 2018, recognizing sustained population growth in the area would soon overmatch the available infrastructure.
When the project was initiated, the plant was already exceeding 90% of its designed capacity, while its Cheat Lake service area was growing by about 3.75% annually.
MUB leadership has noted that the upgrade was designed not only to meet today's needs but make future projects more cost-effective.
As mentioned, improvements include the installation of state-of-the-art ultraviolet disinfection technology that provides advanced treatment while reducing chemical use. Odor control improvements will enhance air quality in areas surrounding the facility, and standby power capabilities will help ensure uninterrupted operations during power outages.
In preparation for the project, Morgantown City Council finalized a 100% rate increase for MUB's Cheat Lake sewer customers in October 2024. Those rates have been in place since Nov. 29 of that year.
According to The Dominion Post archive, the original treatment plant, located at 166 Sunset Beach Road, was built in 1984 with a capacity of 250,000 gallons per day.
MUB took over operation of the plant in 1998 and launched a complete overhaul as part of a $10.3 million system upgrade.
At that time, capacity was expanded to 750,000 gallons per day, and sewer service was extended to more than 1,500 customers in the Cheat Lake area through new interceptors.